Superload Permit Procedures, Time Frames, Cancellation Fees & Re‑Routing Charges Effective Date: 05/27/2026 Applies To: All superload permit applications, engineering reviews, route surveys, escort scheduling, and movement coordination. 1. Definition of a Superload A load is classified as a superload when it exceeds standard oversize/overweight limits and requires additional engineering review, route analysis, or multi‑agency coordination. Any load meeting state‑defined superload thresholds must follow this policy. 2. Required Advance Notice To ensure safe routing and timely approvals, superload permit requests must be submitted according to the following minimum time frames: Standard Superload: 10–15 business days before movement Complex Superload: 15–30 business days before movement Extreme Superload: 30–60 business days before movement Time frames begin only after all required documentation is received. 3. Documentation Requirements Permit processing will not begin until all required documents are submitted, including: Completed permit application Accurate axle weights and spacings Trailer/vehicle configuration Load dimensions (L × W × H) Proposed route or origin/destination Route survey (if required) Any additional engineering or utility information requested Incomplete information will delay processing. 4. Engineering & Route Review Time Frames Depending on load characteristics, additional review time may be required: Route Survey Review: 3–7 business days Bridge/Structure Analysis: 5–20 business days Utility or Railroad Coordination: 10–30 business days Local Jurisdiction Approvals: 5–15 business days (varies by agency) These reviews may run concurrently but can extend based on agency workload. 5. Permit Issuance A permit will be issued only after: All engineering reviews are complete All agencies approve the route All fees are paid Permit issuance may take 24–48 hours after final approval. 6. Movement Window Superload permits include: Specific travel dates and times Weather restrictions Escort requirements Speed and lane‑use limitations Failure to move within the permitted window may require a new permit or re‑approval, which may incur additional charges. 7. Cancellation Policy & Fees 7.1 Cancellation Before Processing Begins If a cancellation request is received before permit processing has started: No cancellation fee applies. 7.2 Cancellation After Processing Has Begun If processing has started, the following fees apply: Administrative Processing Fee: [$10 per permit] All fees incurred up to the cancellation date are non‑refundable. 7.3 Cancellation After Permit Issuance If the permit has already been issued: 100% of permit fees are non‑refundable 8. Re‑Routing Charges Re‑routing may be required due to engineering restrictions, construction, weather, agency requirements, or customer‑requested changes. Re‑routing fees may include: Route Re‑Evaluation Fee: [$10 per permit] Re‑routing may extend processing time by 5–30 business days, depending on complexity. 9. Changes, Delays, or Customer‑Requested Modifications Any change to load configuration, routing, or schedule must be reported immediately. Changes may require: Re‑analysis New approvals Additional fees Extended processing time Failure to disclose changes may result in permit revocation or movement delays. 10. Expedited Requests Expedited processing is not guaranteed and is subject to agency approval. If accepted: Additional expedited fees apply Expedited reviews may still require 5–10 business days depending on complexity 11. Compliance Responsibility The carrier is responsible for: Providing accurate information Complying with all permit conditions Maintaining communication regarding delays or changes Ensuring escorts and equipment meet state requirements Non‑compliance may result in fines, permit revocation, or delays.